Breakup

12.9.2 Out to out width 11.75'' and thickness 1.75'' (Hatil model no-HCL-101-101-Bch-6-88 or equivalent)

For wall finished thickness 5.75'' Hatil model no- HCL-101-101-Bch-6-88 or equivalent

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Door frame:For wall finished thickness 5.75'' Hatil model no- HCL-101-101-Bch-6-88 or equivalent Door frame 17 rft 1803 per rft 1803 30651
2 Mason / Mosaic mistry Mason 0.25 nos 700 per day 700 175
3 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Mason Helper 0.25 nos 550 per day 550 137.5
Sub-Total 30963.5
Contractor's Profit 10% 0.1 3096.35
Contractor's Overhead Expenses 3.5% 0.035 1083.72
Total 35143.57
Add VAT with adjustment factor. 1.08108 7.5% 0.075 2849.48
Grand Total 37993.05
Rate per rft 2234.88
Rate per running metre 7330.41