02.15.1 For Dhaka metropolitan area.

Considering 1000 cft of work in/c compacting, dressing and local carriage For Dhaka metropolitan area Loose earth required in/c 15% shrinkage = 1150 cft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Royalty of earth Royalty for earth 1150 cft 2200 per % 0 cft 2.2 2530
2 5-ton capacity truck-fare including loading & unloading (within 30 km radius) Truck hire charge including cost of labour for loading and unloading 6 trucks 2300 per trip 2300 13800
3 Ordinary labour Labour for local carriage, levelling & compacting etc. complete: Ordinary labour 6 nos 550 per day 550 3300
4 Skilled labour Labour for local carriage, levelling & compacting etc. complete: Skilled labour 1 no 600 per day 600 600
5 Ordinary labour Sundries, T & P etc. 1 LS 550 per day 165 165
Sub-Total 20395
Contractor's Profit 10% 0.1 2039.5
Contractor's Overhead Expenses 3.5% 0.035 713.83
Total 23148.33
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1876.89
Grand Total 25025.22
Rate per cft 25.02
Rate per per cum 883.58