Breakup

12.11.4.1 Garjan veneered (SS Fittings)

Considering 6'-9" x 3'-0"= 20.25 sft (single leaf)

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 250 mm long SS tower bolt (A) Fittings: 250mm long SS tower bolt 1 no 150 each 150 150
3 200 mm long SS socket bolt 200mm SS socket bolt 1 no 220 each 220 220
4 100 mm longs SS hinge 100mm long SS hinges 4 nos 100 each 100 400
5 Nickel plated handle Nickel plated handle 2 nos 80 each 80 160
6 SS Screws SS screws 5 dzn 30 per doz. 30 150
7 Hinged cleats and buffer block Hinged cleats & buffer block 1 set 62 set 62 62
8 Carpenter (B) Labour : Carpenter 0.25 nos 700 per day 700 175
9 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator (B) Labour : Carpenter helper 0.5 nos 550 per day 550 275
10 Garjan veneered flush door shutter (C) Cost of shutter: 36 mm thick & 400 kg/cum 20.25 sft 252 per sft 252 5103
Sub-Total 6695
Contractor's Profit 10% 0.1 669.5
Contractor's Overhead Expenses 3.5% 0.035 234.33
Total 7598.83
Add VAT with adjustment factor. 1.08108 7.5% 0.075 616.12
Grand Total 8214.95
Rate per sft 405.68
Rate per sqm 4366.74