Breakup

12.12.1 Gamari

Considering 5'-0" x 2'-8" = 13.35 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Gamari (a)Cost of wood Frame:(2x5'-0"x2.75"x5.25"=1.003cft+Frame:3x2'-9"x2.75"x5.25"=0.827cft+In horizontal louver blade:2"c/c 2x12x2'-6"x6.25"x1"=2.604cft+Bit:2x4x2'-3"x0.5"x0.5"=0.031cft)=4.465cft 4.465 cft 1900 per cft 1900 8483.5
2 Nails and wires (b) Nails etc. 1.5 kg 70 per kg 70 105
3 Carpenter (c)Labour cost:Labour charge for making louver frames, cutting grooves, fitting, fixing horizontal louver blades, fitting wooden bit etc.: Carpenter 1.5 nos 700 per day 700 1050
4 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper 1.5 nos 550 per day 550 825
5 Seasoning of timber in plant D. Seasoning of timber : Seasoning charge 4.465 cft 165 per cft 165 736.73
6 Ordinary labour Labour for loading, unloading and carriage of timber at both ends (1 x 2) 8.93 cft 550 per day 55 491.15
Sub-Total 11691.38
Contractor's Profit 10% 0.1 1169.14
Contractor's Overhead Expenses 3.5% 0.035 409.2
Total 13269.72
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1075.92
Grand Total 14345.64
Rate per sft 1074.61
Rate per sqm 11567.1