Breakup

02.15.2 For Chattogram / Sylhet metropolitan area and Narayanganj district.

Considering 1000 cft of work in/c compacting, dressing and local carriage For Chattogram / Sylhet metropolitan area and Narayanganj district Loose earth required in/c 15% shrinkage = 1150 cft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Royalty of earth Royalty for earth 1150 cft 2200 per % 0 cft 2.2 2530
2 Carrying charge of earth by 5-ton capacity truck in Narayanganj / Chattogram / Sylhet city Truck hire charge including cost of labour for loading and unloading 6 Trips 2000 per trip 2000 12000
3 Ordinary labour Labour for local carriage, levelling & compacting etc. complete: Ordinary labour 6 nos 550 per day 550 3300
4 Skilled labour Labour for local carriage, levelling & compacting etc. complete: Skilled labour 1 no 600 per day 600 600
Sub-Total 18430
Contractor's Profit 10% 0.1 1843
Contractor's Overhead Expenses 3.5% 0.035 645.05
Total 20918.05
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1696.06
Grand Total 22614.11
Rate per cft 226.14
Rate per per cum 7986.13