Breakup

12.13.4 Myanmar(Burma) Teak

Considering 5'-0" x 2'-8" = 13.35 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Myanmar(Burma) teak (a) Cost of materials : (i)Wood:Outer frame:2x5'-0"x2.75"x5.25"=1.003cft+3x2'-9"x2.75"x5.25=0.827cft+Inner shutter frame 2x2x2'-3.5"x2.25"x1.75"=0.250cft+2x2x2'-4"x2.25"x1.65"=0.255cft+sash,2x3x2'-3.5"x1.25"x1.75"=0.292cft)=2.627cft 2.627 cft 7100 per cft 7100 18651.7
2 5 mm thick clear glass (ii)Cost of 5 mm thick glass:(2x4x2'-4"x0'-6"=9.32sft+Wastage 10% =0.93sft)=10.25sft 10.25 sft 76 per sft 76 779
3 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator (iii) Cost of nails, screws, bit, putty etc.: 1 LS 550 per day 25 25
4 Carpenter Labour: Carpenter 1 no 700 per day 700 700
5 Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper to carpenter 1.5 nos 550 per day 550 825
6 Seasoning of timber in plant Cost of Seasoning : Seasoning of timber : Seasoning charge 2.627 cft 165 per cft 165 433.45
7 Ordinary labour Labour for loading, unloading and carriage of timber at both ends (1 x 2) 5.254 cft 550 per day 55 288.97
Sub-Total 21703.12
Contractor's Profit 10% 0.1 2170.31
Contractor's Overhead Expenses 3.5% 0.035 759.61
Total 24633.04
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1997.27
Grand Total 26630.31
Rate per sft 1994.76
Rate per sqm 21471.6
Help