Considering 2 x 2'-7.25" x 6'-9"= 35.16 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Myanmar(Burma) teak (A)Cost of wood:(Stile:2x7'-0"x6.25"x1.75"=1.063cft+Rail:2x2'-9"x6.25"x1.75"=0.418cft+Bit:2x5'-10"x0.75"x0.75"=0.046cft+Bit:2x1'-9"x0.75"x0.75"=0.014cft)=Wood for one panel=1.541cft,Wood for two panels=3.082cft | 3.082 | cft | 7100 | per cft | 7100 | 21882.2 | |
| 2 | 5 mm thick clear glass (B)5 mm thick glass (2x7'-0"x2'-0"=28+Wastage 5% added)=29.4sft | 29.4 | sft | 76 | per sft | 76 | 2234.4 | |
| 3 | 250 mm long brass tower bolt (C) Fittings: 250mm long Brass tower bolt | 4 | nos | 400 | each | 400 | 1600 | |
| 4 | 100 mm longs brass hinge 100mm long Brass hinges | 8 | nos | 150 | each | 150 | 1200 | |
| 5 | 150 mm Brass handle Brass Handle | 4 | nos | 100 | each | 100 | 400 | |
| 6 | Brass screw/38 mm screw Brass screws | 8 | dzn | 25 | per doz. | 25 | 200 | |
| 7 | Hinged cleats and buffer block Hinged cleats & buffer block | 2 | set | 62 | set | 62 | 124 | |
| 8 | Carpenter (D) Labour for making & fitting fixing : Carpenter | 3 | nos | 700 | per day | 700 | 2100 | |
| 9 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper | 4 | nos | 550 | per day | 550 | 2200 | |
| 10 | Glass pan fitting including putty Glass cutting, fitting etc. complete in/c cost of putty for | 29.4 | sft | 18.7 | per sft | 18.7 | 549.78 | |
| 11 | Seasoning of timber in plant (E) Seasoning of timber : Seasoning charge: (Market rate as | 3.082 | cft | 165 | per cft | 165 | 508.53 | |
| 12 | Ordinary labour Labour for loading, unloading and carriage of timber at both ends (1 x 2) | 6.164 | cft | 550 | per day | 55 | 339.02 | |
| Sub-Total | 33337.93 | |||||||
| Contractor's Profit | 10% | 0.1 | 3333.79 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 1166.83 | |||||
| Total | 37838.55 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 3067.99 | ||||
| Grand Total | 40906.54 | |||||||
| Rate per sft | 1163.45 | |||||||
| Rate per sqm | 12523.38 | |||||||