Considering 5'-0" x 2'-9" = 13.75 sft (double leaf)
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 150 mm long brass tower bolt (a) Fittings: 150mm Brass Tower bolt | 2 | nos | 400 | each | 400 | 800 | |
| 2 | 75 mm longs brass hinge 75mm Brass hinge | 6 | nos | 110 | each | 110 | 660 | |
| 3 | 100 mm Brass handle 100mm Brass Handle | 2 | nos | 200 | each | 200 | 400 | |
| 4 | 225 mm long catch hook 9" long catch hook | 2 | nos | 22 | each | 22 | 44 | |
| 5 | Brass screw/38 mm screw Brass Screws | 3.5 | dzn | 25 | per doz. | 25 | 87.5 | |
| 6 | 3 mm thick clear glass 3 mm glass pan:(14x10"x8"=7.78sft+Add wastage 10%=0.78sft)=8.56 sft | 8.56 | sft | 50 | per sft | 50 | 428 | |
| 7 | Glass pan fitting including putty Fitting fixing of glass pans with necessary iron pins & pucca putty | 7.78 | sft | 18.7 | per sft | 18.7 | 145.49 | |
| 8 | Carpenter (b) Labour : Carpenter | 1.5 | nos | 700 | per day | 700 | 1050 | |
| 9 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper | 2 | nos | 550 | per day | 550 | 1100 | |
| 10 | Kathal (c)Cost of wood:(Vertcal:4x5'-0"x3.75"x1.75"=0.911cft+Horizontal:4x1'-6"x3.75"x1.75"=0.273cft+Sash:2x6x1'-6"x1.75"x1.75"=0.383cft)=1.567cft | 1.567 | cft | 2400 | per cft | 2400 | 3760.8 | |
| 11 | Seasoning of timber in plant (d) Seasoning of timber: Seasoning charge | 1.567 | cft | 165 | per cft | 165 | 258.56 | |
| 12 | Ordinary labour Labour for loading, unloading and carriage of timber at both ends (1 x 2) | 3.134 | cft | 550 | per day | 55 | 172.37 | |
| Sub-Total | 8906.72 | |||||||
| Contractor's Profit | 10% | 0.1 | 890.67 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 311.74 | |||||
| Total | 10109.13 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 819.66 | ||||
| Grand Total | 10928.79 | |||||||
| Rate per sft | 794.84 | |||||||
| Rate per sqm | 8555.66 | |||||||