Considering 1 No. fixed glazed frame For 5'-0" x 2'-0"= 10 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | M.S. angle, T and Z-section, Channel etc. 3/4" x 3/4" x 3/4" x 1/8" Z-section (@0.96 Ib per rft):- 2 x 5'-0" + 2 x 2'-0"= 14.00 rft Add wastage 5%= 0.70 rft = 14.70 rft = 14.11 Ibs | 14.11 | lbs | 70000 | per M. ton | 31.75 | 447.99 | |
| 2 | M.S. plain bar and F.I. bar (non-structural use) (ii) 3/4" x 1/8" F.I. bar to make T-section (@ 0.32 Ibs per rft) for horizontal and vertical divider 2 x (1 x 5'-0") + 2 x (2 x 5 x 1'-0")= 30.00 rft Add wastage 5%= 1.50 rft = 31.50 rft = 20.48 Ibs | 20.48 | lbs | 70000 | per M. ton | 31.75 | 650.24 | |
| 3 | 150 mm long clamp 6" long clamp for chowkat: | 6 | nos | 37 | each | 37 | 222 | |
| 4 | Making steel door-window frame and shutter Manufacturing including fabrication, revetting, welding in/c supply of all necessary incidental materials | 10 | sft | 78 | per sft | 78 | 780 | |
| 5 | Plain concrete (1:2:4) with brick chips Labour charges for fitting fixing in position finished window frames in the building shutter and including embeding clamp in CC (1:2:4) & making grooves and mending good the damage etc. complete. | 1 | no | 20151.67 | % cft | 196.12 | 196.12 | |
| 6 | Carrying cost of steel door and window Carriage charge for iron materials from market to workshop & carrying the finished window from workshop to building site. | 1 | no | 77 | each | 77 | 77 | |
| 7 | 3 mm thick clear glass 3 mm glass panes in/c wastage etc. | 10 | sft | 50 | per sft | 50 | 500 | |
| 8 | Glass pan fitting including putty Fitting fixing of glass panes with necessary iron pins & pucca putty | 10 | sft | 18.7 | per sft | 18.7 | 187 | |
| Sub-Total | 3060.35 | |||||||
| Contractor's Profit | 10% | 0.1 | 306.04 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 107.11 | |||||
| Total | 3473.5 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 281.63 | ||||
| Grand Total | 3755.13 | |||||||
| Rate per sft | 375.5 | |||||||
| Rate per sqm | 4041.88 | |||||||