Considering of = 1 No. door viewer
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Foreign made door viewer Cost of door viewer | 1 | no | 250 | each | 250 | 250 | |
| 2 | Carpenter Labour charge for fitting fixing in position after cutting necessary grooves in door shutters and frame ; Carpenter | 0.1 | no | 700 | per day | 700 | 70 | |
| 3 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Carpenter helper | 0.15 | no | 550 | per day | 550 | 82.5 | |
| Sub-Total | 402.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 40.25 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 14.09 | |||||
| Total | 456.84 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 37.04 | ||||
| Grand Total | 493.88 | |||||||
| Rate per each | 494 | |||||||
| Rate per each | 494 | |||||||