For 1 No. window grill Considering 3'-6" x 4'-6" = 15.75 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | M.S. plain bar and F.I. bar (non-structural use) (a)Materials: (i)F.I.bars:3x4'-0"=12.00rft(@ 1.28 Ibs per rft)=15.36Ibs | 15.36 | Ibs | 70000 | per M. ton | 31.75 | 487.68 | |
| 2 | Grade 300(300Mpa / 300N/mm2 ≈ 43500psi/40 Grade): BDS- 6935-2006 - B300 and Ratio fy to fu =>1.25 (ii)16mm dia M.S.rod(1.043 Ibs per rft):10x4'-6"=45rft=46.94Ibs | 46.94 | Ibs | 65000 | per M. ton | 29.48 | 1383.79 | |
| 3 | Making steel grill (b)Workshop charge: Labour cost for manufacturing, welding including supply of necessary electrode, cutting steel to required sizes etx complete. | 15.75 | sft | 51 | per sft | 51 | 803.25 | |
| 4 | Mason / Mosaic mistry (c)Labour charges: Labour charges for fitting and fixing in position of grills : Mason | 0.25 | sft | 700 | per day | 700 | 175 | |
| 5 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Skilled labour | 0.25 | sft | 550 | per day | 550 | 137.5 | |
| 6 | Local carriage | LS | 50 | |||||
| 7 | Cost of CC (1:1.5:3) in/c mending | LS | 75 | |||||
| Sub-Total | 3112.22 | |||||||
| Contractor's Profit | 10% | 0.1 | 311.22 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 108.93 | |||||
| Total | 3532.37 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 286.41 | ||||
| Grand Total | 3818.78 | |||||||
| Rate per sft | 242.48 | |||||||
| Rate per sqm | 2610.05 | |||||||