Consider 1 No.of Window (2.5' x 6.17')= 15.42 sft = 2.17 sqm
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | MS tube / angle (i) Cost of MS Angle 1.5”x1.5”x1/4" Outer frame = 1 x 2 x 6' -2'' = 12.33 Rft Outer frame = 1 x 2 x 2' -6'' = 5.00 Rft Middle Vertical = 1 x 1 x 6' -2'' = 6.17 Rft Shutter frame = 2 x 2 x 6' -2'' = 24.67 Rft Shutter frame = 1 x 2 x 2' -6'' = 5.00 Rft Middle horizontal = 1 x 3 x 2' -6'' = 7.50 Rft Clamp for frame = 1 x 8 x 1' -0'' = 8.00 Rft Sub-total = 68.67 Rft Add wastage 5.00% = 3.43 Rft Total = 72.10 Rft @ 2.342 lb/ft = 168.86 lb | 168.86 | lb | 76000 | per M.Ton | 34.47 | 5820.6 | |
| 2 | MS tube / angle ii) Cost of Angle 2"x2"x¼” M.S anglel for handle Vertical = 1 x 2 x 0' -5'' = 0.83 Rft Sub-total = 0.83 Rft Add wastage 5.00% = 0.04 Rft Total = 0.87 Rft @ 2.975 lb/ft = 2.59 lb | 2.59 | lb | 76000 | per M.Ton | 34.47 | 89.28 | |
| 3 | M.S. plain bar and F.I. bar (non-structural use) (iii) 1½” x ¼” F.I bar For Vertical = 1 1 x 6' -2'' = 6.17 Rft Horizontal = 1 x 2 x x 2' -6'' = 5.00 Rft For Bolot fittings = 1 x 2 x x 0' -10'' = 1.67 Rft Sub-total = 12.84 Rft Add wastage 5.00% = 0.64 Rft Total = 13.48 Rft @ 1.266 lb/ft = 17.07 lb | 17.07 | lb | 70000 | per M. ton | 31.75 | 541.97 | |
| 4 | MS plate of grade 345 Mpa 1.5 mm thick M.S.Sheet for louver For louver 20 x 2' - 6.0'' x 0' 3.5 = 14.58 Sft Add wastage 5.00% = 0.73 Sft Total = 15.31 Sft @ 2.550 lb/sft = 39.04 lb | 39.04 | lb | 77000 | per M.Ton | 34.92 | 1363.28 | |
| 5 | MS plate of grade 345 Mpa 1.5 mm thick M.S.Sheet for pan For pan 6 x 1' - 3.0'' x 1' 3 = 9.38 Sft Add wastage 5.00% = 0.47 Sft Total = 9.85 Sft @ 2.550 lb/sft = 25.12 lb | 25.12 | lb | 77000 | per M.Ton | 34.92 | 877.19 | |
| 6 | Making steel grill Labour cost for manufacturing, welding including supply of necessary electrode, cutting steel to required sizes, 8 nos hinge etc. complete. | 15.42 | sft | 51 | per sft | 51 | 786.42 | |
| 7 | Mason / Mosaic mistry Mason | 0.75 | no | 700 | per day | 700 | 525 | |
| 8 | Skilled labour Skilled labour | 0.75 | no | 600 | per day | 600 | 450 | |
| 9 | Ordinary labour Carriage charge for steel materials from market to workshop and carrying the window grill from workshop to building site. | 1 | no | 550 | per day | 137.5 | 137.5 | |
| 10 | Plain concrete (1:1.5:3) with brick chips Cost of CC (1:1.5:3) in/c mending good the damages: 8x 0'-6"x 0'-6" x 0'-6" = 1 cft | 1 | cft | 20327.8 | % cft | 203.28 | 203.28 | |
| Sub-Total | 10794.52 | |||||||
| Contractor's Profit | 10% | 0.1 | 1079.45 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 377.81 | |||||
| Total | 12251.78 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 993.39 | ||||
| Grand Total | 13245.17 | |||||||
| Rate per sqm | 6103.69 | |||||||
| Rate per sqm | 6103.69 | |||||||