Breakup

14.2.1 Anodized to any colour

Considering 1 No. door Considering: 3'-6" x 7'-0"= 24.5 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 101.60 mm, 44.45 mm wall frame of 1.5 mm thick (Anodized at any colour) (A) Cost of aluminium section: 101.60 mm, 44.45 mm wall frame of 1.5 mm thick 2 x 7'-0" =14rft 14 rft 154.5 per foot 154.5 2163
2 54 mm, 46 mm shutter side of 2.0 mm thick (Anodized at any colour) 54 mm, 46 mm shutter side of 2 mm thick 2 x 7'-0" = 14rft 14 rft 139 per foot 139 1946
3 16.54 mm, 15.49 mm Door glass bit of 0.99 mm thick (Anodized at any colour) 16.54 mm, 15.49 mm door glass bit of 0.99 mm thick ( 2 x 2 x 7'-0"=28rft+2 x 2 x 3'-6"=14rft)=42rft 42 rft 19 per foot 19 798
4 101.60 mm, 42.93 mm closure section of 1.8 mm thick(Anodized at any colour) 101.60 mm, 42.93 mm closure section of 1.8 mm thick 1 x 3'-3"=3.25rft 3.25 rft 134 per foot 134 435.5
5 101.60 mm closure cover of 1.5 mm thick (Anodized at any colour) 101.60 mm closure cover of 1.5 mm thick 1 x 3'-3"= 3.25rft 3.25 rft 51 per foot 51 165.75
6 101.60 mm, 12.70 mm floor bottom of 4 mm thick (Anodized at any colour) 101.60 mm, 12.70 mm floor bottom of 4 mm thick 1 x 3'-3"=3.25 rft 3.25 rft 140 per foot 140 455
7 82.60 mm, 43.99 mm door shutter bottom of 1.8 mm thick (Anodized at any colour) 82.60 mm, 43.99 mm shutter bottom of 1.8 mm thick 1 x 3'-0"= 3rft 3 rft 176 per foot 176 528
8 51 mm, 43.99 mm door shutter top of 1.8 mm thick (Anodized at any colour) 51 mm, 43.99 mm shutter top of 1.8 mm thick 1 x 3'-0"= 3rft 3 rft 147 per foot 147 441
9 101.60 mm, 38.10 mm, 25.4 mm door handle (short) of 2.3 mm, 2.3 mm, 4.01 mm thick (Anodized at any colour) 101.60 mm, 38.10 mm, 25.4 mm handle (short) of 2.3 mm, 2.3 mm, 4.01 mm thick 1 x 1'-6"= 1.5rft 1.5 rft 194 per foot 194 291
10 Swing door clouser (B) Accessories: Swing door clouser 1 set 3200 set 3200 3200
11 Swing door lock Swing door lock 1 set 750 set 750 750
12 Swing door Mohiar Swing door mohiar 14 rft 5 foot 5 70
13 Skilled technician (C) Labour charge for fabrication, assembling and fitting-fixing in position : Skilled technician 0.75 no 1200 per day 1200 900
14 Semi skilled technician Semi- skilled technician 0.75 no 800 per day 800 600
15 Ordinary labour Tools and plant, sundries etc. 1 LS 550 per day 825 825
Sub-Total 13568.25
Contractor's Profit 10% 0.1 1356.83
Contractor's Overhead Expenses 3.5% 0.035 474.89
Total 15399.97
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1248.64
Grand Total 16648.61
Rate per sft 679.55
Rate per sqm 7314.68