Breakup

14.4.1 Anodized to any colour

Considering 1 No. door Considering 7'-0" x 7'-0"= 49 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 75.50 mm, 17.79 mm outer low bottom of minimum 1.2 mm thick (Anodized at any colour) (A) Cost of aluminium sections : 75.50 mm, 17.79 mm outer bottom of minimum 1.2 mm thick 1 x 7'-0"=7rft 7 rft 90 per foot 90 630
2 75.5 mm, 28.50 mm outer top of minimum 1.2 mm thick (Anodized at any colour) 75.5 mm, 28.50 mm outer top of minimum 1.2 mm thick 1 x 7'-0"=7rft 7 rft 106 per foot 106 742
3 33 mm, 26.80 mm, shutter top of minimum 1.2 mm thick (Anodized at any colour) 33 mm, 26.80 mm shutter top of minimum 1.2 mm thick 1 x 6'-9"=6.75rft 6.75 rft 64 per foot 64 432
4 60 mm, 24.40 mm shutter bottom of minimum 1.2 mm thick (Anodized at any colour) 60 mm, 24.40 mm shutter bottom of minimum 1.2 mm thick 1 x 6'-9"= 6.75rft 6.75 rft 89 per foot 89 600.75
5 75.50 mm, 19.90 mm outer side of minimum 1.2 mm thick (Anodized at any colour) 75.50 mm, 19.90 mm outer side of minimum 1.2 mm thick 2 x 7'-0"= 14rft 14 rft 80 per foot 80 1120
6 49.20 mm, 25.80 mm shutter lock of minimum 1.2 mm thick (Anodized at any colour) 49.20 mm, 25.80 mm shutter lock of minimum 1.2 mm thick 2 x 7'-0"=14rft 14 rft 82 per foot 82 1148
7 34.40 mm, 32.10 mm shutter inter lock of minimum 1.2 mm thick (Anodized at any colour) 34.40 mm, 32.13 mm inter lock of minimum 1.2 mm thick 2 x 7'-0"=14rft 14 rft 85 per foot 85 1190
8 Sliding door lock (B) Cost of accessories: Sliding door key lock 2 sets 200 set 200 400
9 Sliding door show lock Sliding door show lock 2 sets 110 set 110 220
10 Sliding door /window wheel Sliding door wheel 4 nos 80 no 80 320
11 Sliding door /window Mohiar Sliding door mohiar 50 rft 1.5 foot 1.5 75
12 Sliding Neoprene Sliding door neoprene 50 rft 2.8 foot 2.8 140
13 Skilled technician (C) Labour charge for fabrication, assembling and fitting-fixing in position: Skilled technician 2 no 1200 per day 1200 2400
14 Semi skilled technician Semi- skilled technician 2 no 800 per day 800 1600
15 Ordinary labour Tools and plant, sundries etc. 1 LS 550 per day 825 825
Sub-Total 11842.75
Contractor's Profit 10% 0.1 1184.28
Contractor's Overhead Expenses 3.5% 0.035 414.5
Total 13441.53
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1089.85
Grand Total 14531.38
Rate per sft 296.55
Rate per sqm 3192.06