Breakup

14.4.2 Powder coated to any colour

Considering 1 No. door Considering 7'-0" x 7'-0"= 49 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 75.50 mm, 17.79 mm outer low bottom of minimum 1.2 mm thick (Powder coated at any colour) (A) Cost of aluminium sections: 75.50 mm, 17.79 mm outer bottom of minimum 1.2 mm thick 1 x 7'-0"=7rft 7 rft 113 per foot 113 791
2 75.5 mm, 28.50 mm outer top of minimum 1.2 mm thick(Powder coated at any colour) 75.5 mm, 28.50 mm outer top of minimum 1.2 mm thick 1 x 7'-0"=7rft 7 rft 126 per foot 126 882
3 33 mm, 26.80 mm, shutter top of 1.3 mm thick (Powder coated at any colour) 33 mm, 26.80 mm shutter top of minimum 1.2 mm thick 1 x 6'-9"=6.75rft 6.75 rft 87.5 per foot 87.5 590.63
4 60 mm, 24.40 mm shutter bottom of minimum 1.2 mm thick (Powder coated at any colour) 60 mm, 24.40 mm shutter bottom of minimum 1.2 mm thick 1 x 6'-9"=6.75rft 6.75 rft 123.5 per foot 123.5 833.63
5 75.50 mm, 19.90 mm outer side of minimum 1.2 mm thick (Powder coated at any colour) 75.50 mm, 19.90 mm outer side of minimum 1.2 mm thick 2 x 7'-0"=14rft 14 rft 105 per foot 105 1470
6 49.20 mm, 25.80 mm shutter lock of minimum 1.2 mm thick (Powder coated at any colour) 49.20 mm, 25.80 mm shutter lock of minimum 1.2 mm thick 2 x 7'-0"=14rft 14 rft 116.5 per foot 116.5 1631
7 34.40 mm, 32.10 mm shutter inter lock of minimum 1.2 mm thick (Powder coated at any colour) 34.40 mm, 32.13 mm inter lock of minimum 1.2 mm thick 2 x 7'-0"=14rft 14 rft 111 per foot 111 1554
8 Sliding door lock (B) Cost of accessories: Sliding door key lock 2 sets 200 set 200 400
9 Sliding door show lock Sliding door show lock 2 sets 110 set 110 220
10 Sliding door /window wheel Sliding door wheel 4 nos 80 no 80 320
11 Sliding door /window Mohiar Sliding door mohiar 50 rft 1.5 foot 1.5 75
12 Sliding Neoprene Sliding door neoprene 50 rft 2.8 foot 2.8 140
13 Skilled technician (C) Labour charge for fabrication, assembling and fitting-fixing in position : Skilled technician 2 nos 1200 per day 1200 2400
14 Semi skilled technician Semi- skilled technician 2 nos 800 per day 800 1600
15 Ordinary labour Tools and plant, sundries etc. 1 LS 550 per day 825 825
Sub-Total 13732.26
Contractor's Profit 10% 0.1 1373.23
Contractor's Overhead Expenses 3.5% 0.035 480.63
Total 15586.12
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1263.74
Grand Total 16849.86
Rate per sft 343.88
Rate per sqm 3701.52