14.5.1 Anodized to any colour

Considering 1 No. door Considering 6'-0" x 7'-0" = 42 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 95 mm, 22.39 mm outer bottom (low) of minimum 1.2 mm thick (Anodized at any colour) (A) Cost of aluminium sections: 95 mm, 22.39 mm outer bottom (low) of minimum 1.2 mm thick 1 x 6'-0"= 6rft 6 rft 105.5 per foot 105.5 633
2 95.5 mm, 28.50 mm outer top of minimum 1.2 mm thick (Anodized at any colour) 95.00 mm, 28.50 mm outer top of minimum 1.2 mm thick 1 x 6'-0"= 6rft 6 rft 119 per foot 119 714
3 33 mm, 26.80 mm, shutter top of minimum 1.2 mm thick (Anodized at any colour) 33 mm, 26.80 mm shutter top of minimum 1.2 mm thick 1 x 5'-9"=5.75rft 5.75 rft 64 per foot 64 368
4 60 mm, 24.40 mm shutter bottom of minimum 1.2 mm thick (Anodized at any colour) 60 mm, 24.40 mm shutter bottom of minimum 1.2 mm thick 1 x 5'-9"= 5.75rft 5.75 rft 89 per foot 89 511.75
5 95.00 mm, 19.50 mm outer side of minimum 1.2 mm thick (Anodized at any colour) 95.00 mm, 19.50 mm outer side of minimum 1.2 mm thick 2 x 7'-0"=14rft 14 rft 95 per foot 95 1330
6 49.20 mm, 25.80 mm shutter lock of minimum 1.2 mm thick (Anodized at any colour) 49.20 mm, 25.80 mm shutter lock of minimum 1.2 mm thick 2 x 7'-0"=14rft 14 rft 82 per foot 82 1148
7 34.40 mm, 32.10 mm shutter inter lock of minimum 1.2 mm thick (Anodized at any colour) 34.40 mm, 32.13 mm interlock of minimum 1.2 mm thick 2 x 7'-0"= 14rft 14 rft 85 per foot 85 1190
8 42.2 mm, 13.2 mm net section of minimum 1.2 mm thickness (Anodized at any colour) 42.20 mm, 13.20 mm net section of minimum 1.2 mm thick (2 x 7'-0"=14rft + 2 x 6'-0"=12rft)= 26rft 26 rft 61 per foot 61 1586
9 Mosquito net (fiber net) Fiber net mesh 6'-0" x 7'-0"= 42sft 42 sft 20 per sft 20 840
10 Sliding door lock (B) Cost of accessories: Sliding door key lock 2 sets 200 set 200 400
11 Sliding door show lock Sliding door show lock 2 sets 110 set 110 220
12 Sliding door /window wheel Sliding door wheel 4 nos 80 no 80 320
13 Sliding door /window Mohiar Sliding door mohiar 46 rft 1.5 foot 1.5 69
14 Sliding Neoprene Sliding door neoprene 52 rft 2.8 foot 2.8 145.6
15 Skilled technician (C) Labour charge for fabrication, assembling and fitting-fixing in position: Skilled technician 2 nos 1200 per day 1200 2400
16 Semi skilled technician Semi- skilled technician 2 nos 800 per day 800 1600
17 Ordinary labour Tools and plant, sundries etc. 1 LS 550 per day 825 825
Sub-Total 14300.35
Contractor's Profit 10% 0.1 1430.04
Contractor's Overhead Expenses 3.5% 0.035 500.51
Total 16230.9
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1316.02
Grand Total 17546.92
Rate per sft 417.79