Breakup

14.5.2 Powder coated to any colour

Considering 1 No. door Considering 6'-0" x 7'-0" = 42 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 95 mm, 22.39 mm outer bottom (low) of minimum 1.2 mm thick (Powder coated at any colour) (A) Cost of aluminium sections : 95 mm, 22.39 mm outer bottom (low) of minimum 1.2 mm thick 1 x 6'-0"=6rft 6 rft 121 per foot 121 726
2 95.5 mm, 28.50 mm outer top of minimum 1.2 mm thick (Powder coated at any colour) 95.00 mm, 28.50 mm outer top of minimum 1.2 mm thick 1 x 6'-0"=6rft 6 rft 180 per foot 180 1080
3 33 mm, 26.80 mm, shutter top of 1.3 mm thick (Powder coated at any colour) 33 mm, 26.80 mm shutter top of minimum 1.2 mm thick 1 x 5'-9"=5.75rft 5.75 rft 87.5 per foot 87.5 503.13
4 60 mm, 24.40 mm shutter bottom of minimum 1.2 mm thick (Powder coated at any colour) 60 mm, 24.40 mm shutter bottom of minimum 1.2 mm thick 1 x 5'-9"=5.75rft 5.75 rft 123.5 per foot 123.5 710.13
5 95.00 mm, 19.50 mm outer side of minimum 1.2 mm thick (Powder coated at any colour) 95.00 mm, 19.50 mm outer side of minimum 1.2 mm thick 2 x 7'-0"=14rft 14 rft 126.5 per foot 126.5 1771
6 49.20 mm, 25.80 mm shutter lock of minimum 1.2 mm thick (Powder coated at any colour) 49.20 mm, 25.80 mm shutter lock of minimum 1.2 mm thick 2 x 7'-0"=14rft 14 rft 116.5 per foot 116.5 1631
7 34.40 mm, 32.10 mm shutter inter lock of minimum 1.2 mm thick (Powder coated at any colour) 34.40 mm, 32.13 mm interlock of minimum 1.2 mm thick 2 x 7'-0"=14rft 14 rft 111 per foot 111 1554
8 42.2 mm, 13.2 mm net section of minimum 1.2 mm thickness (Powder coated at any colour) 42.20 mm, 13.20 mm net section of minimum 1.2 mm thick ( 2 x 7'-0"=14rft + 2 x 6'-0"=12rft)= 26rft 26 rft 79 per foot 79 2054
9 Mosquito net (fiber net) Fiber net mesh 6'-0" x 7'-0"= 42rft 42 rft 20 per sft 20 840
10 Sliding door lock (B) Cost of accessories: Sliding door key lock 2 sets 200 set 200 400
11 Sliding door show lock Sliding door show lock 2 sets 110 set 110 220
12 Sliding door /window wheel Sliding door wheel 4 nos 80 no 80 320
13 Sliding door /window Mohiar Sliding door mohiar 46 rft 1.5 foot 1.5 69
14 Sliding Neoprene Sliding neoprene 52 rft 2.8 foot 2.8 145.6
15 Skilled technician (C) Labour charge for fabrication, assembling and fitting-fixing in position : Skilled technician 2 nos 1200 per day 1200 2400
16 Semi skilled technician Semi- skilled technician 2 nos 800 per day 800 1600
17 Ordinary labour Tools and plant, sundries etc. 1 LS 550 per day 825 825
Sub-Total 16848.86
Contractor's Profit 10% 0.1 1684.89
Contractor's Overhead Expenses 3.5% 0.035 589.71
Total 19123.46
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1550.55
Grand Total 20674.01
Rate per sft 492.24
Rate per sqm 5298.47