Breakup

14.7.1.1 Anodized to any colour

Considering 1 No. window Considering 5'-0" x 4'-6" = 22.5 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 75.50 mm, 32 mm outer bottom (high) of minimum 1.2 mm thick (Anodized at any colour) (A) Cost of aluminium sections: 75.50 mm, 32 mm outer bottom (high) of minimum 1.2 mm thick 1 x 5'-0"=5rft 5 rft 98 per foot 98 490
2 75.5 mm, 28.50 mm outer top of minimum 1.2 mm thick (Anodized at any colour) 75.5 mm, 28.50 mm outer top of minimum 1.2 mm thick 1x 5'-0"=5rft 5 rft 106 per foot 106 530
3 33 mm, 26.80 mm, shutter top of minimum 1.2 mm thick (Anodized at any colour) 33 mm, 26.80 mm shutter top of minimum 1.2 mm thick 1 x 4'-9"= 4.75 4.75 rft 64 per foot 64 304
4 60 mm, 24.40 mm shutter bottom of minimum 1.2 mm thick (Anodized at any colour) 60 mm, 24.40 mm shutter bottom of minimum 1.2 mm thick 1 x 4'-9"= 4.75rft 4.75 rft 89 per foot 89 422.75
5 75.50 mm, 19.90 mm outer side of minimum 1.2 mm thick (Anodized at any colour) 75.50 mm, 19.90 mm outer side of minimum 1.2 mm thick 2 x 4'-6"=9rft 9 rft 80 per foot 80 720
6 49.20 mm, 25.80 mm shutter lock of minimum 1.2 mm thick (Anodized at any colour) 49.20 mm, 25.80 mm shutter lock of minimum 1.2 mm thick 2 x 4'-6"= 9rft 9 rft 82 per foot 82 738
7 34.40 mm, 32.10 mm shutter inter lock of minimum 1.2 mm thick (Anodized at any colour) 34.40 mm, 32.13 mm inter-lock of minimum 1.2 mm thick 2 x 4'-6"=9rft 9 rft 85 per foot 85 765
8 Sliding window key lock (B) Cost of accessories: Sliding window key lock 2 sets 90 set 90 180
9 Sliding door /window wheel Sliding window wheel 4 nos 80 no 80 320
10 Sliding door /window Mohiar Sliding window mohiar 33 rft 1.5 foot 1.5 49.5
11 Sliding Neoprene Sliding neoprene 28 rft 2.8 foot 2.8 78.4
12 Skilled technician (C) Labour charge for fabrication, assembling and fitting-fixing in position : Skilled technician 0.5 no 1200 per day 1200 600
13 Semi skilled technician Semi- skilled technician 0.5 no 800 per day 800 400
14 Ordinary labour Tools and plant, sundries etc. 1 LS 550 per day 660 660
Sub-Total 6257.65
Contractor's Profit 10% 0.1 625.76
Contractor's Overhead Expenses 3.5% 0.035 219.02
Total 7102.43
Add VAT with adjustment factor. 1.08108 7.5% 0.075 575.87
Grand Total 7678.3
Rate per sft 341.24
Rate per sqm 3673.11
Help