14.7.2.2 Powder coated to any colour

Considering 1 No. window Considering 3'-0" x 4'-6" = 13.5 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 75.50 mm, 32 mm outer bottom (high) of minimum 1.2 mm thick (Powder coated at any colour) (A) Cost of aluminium sections: 75.50 mm, 32 mm outer bottom (high) of minimum 1.2 mm thick 1 x 3'-0"=3rft 3 rft 123.5 per foot 123.5 370.5
2 75.5 mm, 28.50 mm outer top of minimum 1.2 mm thick(Powder coated at any colour) 75.5 mm, 28.50 mm outer top of minimum 1.2 mm thick 1x 3'-0"= 3rft 3 rft 126 per foot 126 378
3 33 mm, 26.80 mm, shutter top of 1.3 mm thick (Powder coated at any colour) 33 mm, 26.80 mm shutter top of minimum 1.2 mm thick 1 x 2'-9"= 2.75rft 2.75 rft 87.5 per foot 87.5 240.63
4 60 mm, 24.40 mm shutter bottom of minimum 1.2 mm thick (Powder coated at any colour) 60 mm, 24.40 mm shutter bottom of minimum 1.2 mm thick 1 x 2'-9"=2.75rft 2.75 rft 123.5 per foot 123.5 339.63
5 75.50 mm, 19.90 mm outer side of minimum 1.2 mm thick (Powder coated at any colour) 75.50 mm, 19.90 mm outer side of minimum 1.2 mm thick 2 x 4'-6"=9rft 9 rft 105 per foot 105 945
6 49.20 mm, 25.80 mm shutter lock of minimum 1.2 mm thick (Powder coated at any colour) 49.20 mm, 25.80 mm shutter lock of minimum 1.2 mm thick 2 x 4'-6"=9rft 9 rft 116.5 per foot 116.5 1048.5
7 34.40 mm, 32.10 mm shutter inter lock of minimum 1.2 mm thick (Powder coated at any colour) 34.40 mm, 32.13 mm inter-lock of minimum 1.2 mm thick 2 x 4'-6"= 9rft 9 rft 111 per foot 111 999
8 Sliding door lock (B) Cost of accessories: Sliding window key lock 2 set 200 set 200 400
9 Sliding door /window wheel Sliding window wheel 4 nos 80 no 80 320
10 Sliding door /window Mohiar Sliding window mohiar 27 rft 1.5 foot 1.5 40.5
11 Sliding Neoprene Sliding neoprene 24 rft 2.8 foot 2.8 67.2
12 Skilled technician (C) Labour charge for fabrication, assembling and fitting-fixing in position : Skilled technician 0.33333 no 1200 per day 1200 400
13 Semi skilled technician Semi- skilled technician 0.333333 no 800 per day 800 266.67
14 Ordinary labour Tools and plant, sundries etc. 1 LS 550 per day 550 550
Sub-Total 6365.63
Contractor's Profit 10% 0.1 636.56
Contractor's Overhead Expenses 3.5% 0.035 222.8
Total 7224.99
Add VAT with adjustment factor. 1.08108 7.5% 0.075 585.81
Grand Total 7810.8
Rate per sft 578.59
Rate per sqm 6227.94