Breakup

14.9.3.1 Anodized to any colour

Considering 1 No. window Considering 2'-6" x 2'-0"= 5 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 91.50 mm, 38.00 mm outer bottom of 1.5 mm thick EDF(Anodized at any colour) (A) Cost of aluminium sections : 91.50 mm, 38.00 mm outer bottom of 1.5 mm thick 1 x 2'-6"= 2.5rft 2.5 rft 124.5 per foot 124.5 311.25
2 91.00 mm, 28.70 mm outer top of 1.5 mm thick EDF(Anodized at any colour) 91.00 mm, 28.70 mm outer top of 1.5 mm thick 1 x 2'-6"= 2.5rft 2.5 rft 133 per foot 133 332.5
3 65.00 mm, 27.30 mm shutter topof 1.5 mm thick EDF(Anodized at any colour) 65.00 mm, 27.30 mm shutter top of 1.5 mm thick 1 x 2'-3"= 2.25rft 2.25 rft 119 per foot 119 267.75
4 72.20 mm, 24.65 mm shutter bottom of 1.5 mm thick EDF(Anodized at any colour) 72.20 mm, 24.65 mm shutter bottom of 1.5 mm thick 1 x 2'-6"= 2.5rft 2.5 rft 129 per foot 129 322.5
5 91.50 mm, 28.50 mm outer side of 1.5 mm thick EDF(Anodized at any colour) 91.50 mm, 28.50 mm outer side of 1.5 mm thick 2 x 2'-0"= 4rft 4 rft 125.5 per foot 125.5 502
6 65.30 mm, 26.00 mm shutter lock of 1.5 mm thick EDF(Anodized at any colour) 65.30 mm, 26.00 mm shutter lock of 1.5 mm thick 2 x 2'-0"=4rft 4 rft 109.5 per foot 109.5 438
7 55.20 mm, 26.00 mm inter lock of 1.5 mm thick EDF(Anodized at any colour) 55.20 mm, 26.00 mm inter lock of 1.5 mm thick 2 x 2'-0"= 4rft 4 rft 118 per foot 118 472
8 55.20 mm, 13.20 mm net section of 1.5 mm thick EDF(Anodized at any colour) 55.20 mm, 13.20 mm net section of 1.5 mm thick (2 x 2'-0"= 4rft + 2 x 1'-3"= 2.5rft)= 6.5rft 6.5 rft 85.5 per foot 85.5 555.75
9 Mosquito net (fiber net) Fiber net mesh 1'-3" x 2'-6"= 3.12sft 3.12 sft 20 per sft 20 62.4
10 Sliding window key lock (B) Cost of accessories: Sliding window key lock 2 sets 90 set 90 180
11 Sliding door /window wheel Sliding window wheel 4 nos 80 no 80 320
12 Sliding door /window Mohiar Sliding window mohiar 10 rft 1.5 foot 1.5 15
13 Sliding Neoprene Sliding window neoprene 8 rft 2.8 foot 2.8 22.4
14 Sealant Sealant 50 gm 3.1 gm 3.1 155
15 Skilled technician (C) Labour charge for fabrication, assembling and fitting-fixing in position : Skilled technician 0.3333333 no 1200 per day 1200 400
16 Semi skilled technician Semi- skilled technician 0.33333333 no 800 per day 800 266.67
17 Ordinary labour Tools and plant, sundries etc. 1 LS 550 per day 550 550
Sub-Total 5173.22
Contractor's Profit 10% 0.1 517.32
Contractor's Overhead Expenses 3.5% 0.035 181.06
Total 5871.6
Add VAT with adjustment factor. 1.08108 7.5% 0.075 476.08
Grand Total 6347.68
Rate per sft 1269.6
Rate per sqm 13665.97