Breakup

14.9.3.2 Powder coated to any colour

Considering 1 No. window Considering 2'-6" x 2'-0"= 5 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 91.50 mm, 38.00 mm outer bottom of 1.5 mm thick EDF(Powder coated at any colour) (A) Cost of aluminium sections : 91.50 mm, 38.00 mm outer bottom of 1.5 mm thick 1 x 2'-6"= 2.5rft 2.5 rft 143 per foot 143 357.5
2 91.00 mm, 28.70 mm outer top of 1.5 mm thick EDF(Powder coated at any colour) 91.00 mm, 28.70 mm outer top of 1.5 mm thick 1 x 2'-6"= 2.5rft 2.5 rft 152.5 per foot 152.5 381.25
3 65.00 mm, 27.30 mm shutter topof 1.5 mm thick EDF(Powder coated at any colour) 65.00 mm, 27.30 mm shutter top of 1.5 mm thick 1 x 2'-3"= 2.25rft 2.25 rft 136 per foot 136 306
4 72.20 mm, 24.65 mm shutter bottom of 1.5 mm thick EDF(Powder coated at any colour) 72.20 mm, 24.65 mm shutter bottom of 1.5 mm thick 1 x 2'-6"= 2.5rft 2.5 rft 148 per foot 148 370
5 91.50 mm, 28.50 mm outer side of 1.5 mm thick EDF(Powder coated at any colour) 91.50 mm, 28.50 mm outer side of 1.5 mm thick 2 x 2'-0"= 4rft 4 rft 144 per foot 144 576
6 65.30 mm, 26.00 mm shutter lock of 1.5 mm thick EDF(Powder coated at any colour) 65.30 mm, 26.00 mm shutter lock of 1.5 mm thick 2 x 2'-0"=4rft 4 rft 125.5 per foot 125.5 502
7 55.20 mm, 26.00 mm inter lock of 1.5 mm thick EDF(Powder coated at any colour) 55.20 mm, 26.00 mm inter lock of 1.5 mm thick 2 x 2'-0"= 4rft 4 rft 135 per foot 135 540
8 55.20 mm, 13.20 mm net section of 1.5 mm thick EDF(Powder coated at any colour) 55.20 mm, 13.20 mm net section of 1.5 mm thick (2 x 2'-0"= 4rft + 2 x 1'-3"= 2.5rft) = 6.5rft 6.5 rft 98 per foot 98 637
9 Mosquito net (fiber net) Fiber net mesh 1'-3" x 2'-6"= 3.12sft 3.12 sft 20 per sft 20 62.4
10 Sliding window key lock (B) Cost of accessories: Sliding window key lock 2 sets 90 set 90 180
11 Sliding door /window wheel Sliding window wheel 4 nos 80 no 80 320
12 Sliding door /window Mohiar Sliding window mohiar 10 rft 1.5 foot 1.5 15
13 Sliding Neoprene Sliding window neoprene 8 rft 2.8 foot 2.8 22.4
14 Sealant Sealant 50 gm 3.1 gm 3.1 155
15 Skilled technician (C) Labour charge for fabrication, assembling and fitting-fixing in position : Skilled technician 0.3333333 no 1200 per day 1200 400
16 Semi skilled technician Semi- skilled technician 0.33333333 no 800 per day 800 266.67
17 Ordinary labour Tools and plant, sundries etc. 1 LS 550 per day 550 550
Sub-Total 5641.22
Contractor's Profit 10% 0.1 564.12
Contractor's Overhead Expenses 3.5% 0.035 197.44
Total 6402.78
Add VAT with adjustment factor. 1.08108 7.5% 0.075 519.14
Grand Total 6921.92
Rate per sft 1384.4
Rate per sqm 14901.68