Breakup

14.11.2 Powder coated to any colour

Considering 1 No. window Considering 3'-0" x 4'-0" = 12 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 38.88 mm, 36.63 mm casement outer 1.5 mm thick (Powder coated at any colour) (A) Cost of aluminium sections: 38.88 mm, 36.63 mm casement outer 1.5 mm thick (2 x 4'-0"=8rft + 2 x 3'-0"= 6rft)= 14rft 14 rft 66.5 per foot 66.5 931
2 47.62 mm, 28.57 mm, 40.82 mm casement shutter of 1.9 mm thick(Powder coated at any colour) 47.62 mm, 28.57 mm, 40.82 mm casement shutter of 1.9 mm thick ( 2 x 4'-0"= 16rft + 2 x 3'-0"= 6rft)= 22rft 22 rft 116 per foot 116 2552
3 15.87 mm, 27.00 mm casement glass clip of 1.245 mm thick(Powder coated at any colour) 15.87 mm, 27.00 mm shutter glass clip of 1.245 mm thick (2 x 4'-0"= 16rft + 2 x 3'-0"=6rft)- 22rft 22 rft 33.5 per foot 33.5 737
4 1 in square pipe(Powder coated at any colour) 1" x 1" square pipe 4 rft 52.5 per foot 52.5 210
5 4-bar hinge (B) Cost of accessories: 4-bar hinge 2 nos 750 each 750 1500
6 Casement handle Casement handle 2 nos 270 each 270 540
7 Skilled technician (C) Labour charge for fabrication, assembling and fitting-fixing in position : Skilled technician 1.5 nos 1200 per day 1200 1800
8 Semi skilled technician Semi- skilled technician 1.5 nos 800 per day 800 1200
9 Ordinary labour Tools and plant, sundries etc. 1 LS 550 per day 550 550
Sub-Total 10020
Contractor's Profit 10% 0.1 1002
Contractor's Overhead Expenses 3.5% 0.035 350.7
Total 11372.7
Add VAT with adjustment factor. 1.08108 7.5% 0.075 922.11
Grand Total 12294.81
Rate per sft 1024.58
Rate per sqm 11028.58