Breakup

14.12.2.2 Powder coated to any colour

Considering 1 No. of curtain Considering 10'-0" x 2'-6"= 25 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 17.40 mm, 31.78 mm bottom cover of minimum 1.2 mm thick (Powder coated at any colour) (A) Cost of aluminium sections : 17.40 mm, 31.78 mm bottom cover of minimum 1.2 mm thick 1 x 10'-0"=10rft 10 rft 53.5 per foot 53.5 535
2 76.20 mm, 38.10 mm fixed bottom of minimum 1.2 mm thick(Powder coated at any colour) 76.20 mm, 38.10 mm fixed bottom of minimum 1.2 mm thick 1 x 10'-0"= 10rft 10 rft 139 per foot 139 1390
3 57.15 mm, 15.88 mm grouve cover of minimum 1.2 mm thick (Powder coated at any colour) 57.15 mm, 15.80 mm grouve cover of minimum 1.2 mm thick (4 x 4'-6"=10rft + 1 x 10'-0"=10rft)=20rft 20 rft 81 per foot 81 1620
4 76.20 mm, 38.10 mm, 57.15 mm fixed top & side of minimum 1.2 mm thick(Powder coated at any colour) 76.20 mm, 38.10 mm top & side of minimum 1.2 mm thick (4 x 4'-6"=10rft + 1 x 10'-0"=10rft)=20rft 20 rft 156.5 per foot 156.5 3130
5 7.14 mm spandrel of 1.5 mm thick (Powder coated at any colour) 7.14 mm spandrel of 1.5 mm thick 1 x 60'-0"= 60rft 60 rft 138 per foot 138 8280
6 Rivet (B) Cost of accessories: Rivet 88 pcs 5 each 5 440
7 S.S. screws Screws 28 pcs 2.5 each 2.5 70
8 Skilled technician (C) Labour charge for fabrication, assembling and fitting-fixing in position : Skilled technician 1 no 1200 per day 1200 1200
9 Semi skilled technician Semi- skilled technician 1 no 800 per day 800 800
10 Ordinary labour Tools and plant, sundries etc. 1 LS 550 per day 1100 1100
Sub-Total 18565
Contractor's Profit 10% 0.1 1856.5
Contractor's Overhead Expenses 3.5% 0.035 649.78
Total 21071.28
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1708.48
Grand Total 22779.76
Rate per sft 911.2
Rate per sqm 9808.16