Considering 1 No. fan-light Considering 5'-0" x 2'-3"= 11.25 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 17.40 mm, 31.78 mm bottom cover of minimum 1.2 mm thick (Powder coated at any colour) (A) Cost aluminium sections: 17.40 mm, 31.78 mm bottom cover of minimum 1.2 mm thick 1 x 5'-0"=5rft | 5 | rft | 53.5 | per foot | 53.5 | 267.5 | |
| 2 | 76.20 mm, 38.10 mm fixed bottom of minimum 1.2 mm thick(Powder coated at any colour) 76.20 mm, 38.10 mm fixed bottom of minimum 1.2 mm thick 1 x 5'-0"=5rft | 5 | rft | 139 | per foot | 139 | 695 | |
| 3 | 57.15 mm, 15.88 mm grouve cover of minimum 1.2 mm thick (Powder coated at any colour) 57.15 mm, 15.88 mm grouve cover of minimum 1.2 mm thick 1 x 2'-3"=2.25rft | 2.25 | rft | 81 | per foot | 81 | 182.25 | |
| 4 | 76.20 mm, 38.10 mm, 57.15 mm fixed top & side of minimum 1.2 mm thick(Powder coated at any colour) 76.20 mm, 38.10 mm top & side of minimum 1.2 mm thick (3 x 2'-3"=6.75rft + 1 x 5'-0"=5rft)=11.75rft | 11.75 | rft | 156.5 | per foot | 156.5 | 1838.88 | |
| 5 | Sliding Neoprene (B) Cost of accessories: Neoprene | 40 | rft | 2.8 | foot | 2.8 | 112 | |
| 6 | Ordinary labour Bolts & nuts | 1 | LS | 550 | per day | 916.67 | 916.67 | |
| 7 | Skilled technician (C) Labour charge for fabrication, assembling and fitting-fixing in position : Skilled technician | 0.5 | no | 1200 | per day | 1200 | 600 | |
| 8 | Semi skilled technician Semi- skilled technician | 0.5 | no | 800 | per day | 800 | 400 | |
| 9 | Ordinary labour Tools and plant, sundries etc. | 1 | LS | 550 | per day | 330 | 330 | |
| Sub-Total | 5342.3 | |||||||
| Contractor's Profit | 10% | 0.1 | 534.23 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 186.98 | |||||
| Total | 6063.51 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 491.64 | ||||
| Grand Total | 6555.15 | |||||||
| Rate per sft | 582.67 | |||||||
| Rate per sqm | 6271.86 | |||||||