14.14.1 Anodized to any colour

Considering 1 No. fixed louver Considering 4'-0" x 2'-3"= 9 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 76.00 mm, 38.10 mm wall frame of minimum 1.2 mm thick (Anodized at any colour) (A) Cost aluminium sections: 76.00 mm, 38.10 mm wall frame of minimum 1.2 mm thick (2 x 4'-0"=8rft + 2 x 2'-3"= 4.5rft)= 12.5rft 12.5 rft 97 per foot 97 1212.5
2 55.02 mm, 37.39 mm louver Z-section of 1.5 mm thick (Anodized at any colour) 55.02 mm, 37.39 mm louver section of 1.5 mm thick 2 x 9 x 4'-0"= 72rft 72 rft 54 per foot 54 3888
3 39.67 mm, 15.06 mm louver outer U-section of minimum 1.2 mm thick (Anodized at any colour) 39.67 mm, 15.06 mm louver outer of minimum 1.2 mm thick 2 x 2'-3"= 4.5rft 4.5 rft 39 per foot 39 175.5
4 Ordinary labour (B) Cost of accessories: Machineries charges 1 LS 550 per day 550 550
5 Ordinary labour Bolts & nuts 1 LS 550 per day 440 440
6 Skilled technician (C) Labour charge for fabrication, assembling and fitting-fixing in position : Skilled technician 0.33 no 1200 per day 1200 396
7 Semi skilled technician Semi- skilled technician 0.33 no 800 per day 800 264
8 Ordinary labour Tools and plant, sundries etc. 1 LS 550 per day 330 330
Sub-Total 7256
Contractor's Profit 10% 0.1 725.6
Contractor's Overhead Expenses 3.5% 0.035 253.96
Total 8235.56
Add VAT with adjustment factor. 1.08108 7.5% 0.075 667.75
Grand Total 8903.31
Rate per sft 989.22
Rate per sqm 10647.96