Breakup

14.14.2 Powder coated to any colour

Considering 1 No. fixed louver Considering 4'-0" x 2'-3"= 9 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 76.00 mm, 38.10 mm wall frame of minimum 1.2 mm thick (Powder coated at any colour) (A) Cost aluminium sections: 76.00 mm, 38.10 mm wall frame of minimum 1.2 mm thick (2 x 4'-0"=8rft + 2 x 2'-3"=4.5rft)= 12.5rft 12.5 rft 123 per foot 123 1537.5
2 55.02 mm, 37.39 mm louver Z-section of 1.5 mm thick (Powder coated at any colour) 55.02 mm, 37.39 mm louver section of 1.5 mm thick 2 x 9 x 4'-0"= 72rft 72 rft 62 per foot 62 4464
3 39.67 mm, 15.06 mm louver outer U-section of minimum 1.2 mm thick (Powder coated at any colour) 39.67 mm, 15.06 mm louver outer of minimum 1.2 mm thick 2 x 2'-3"= 4.5 4.5 rft 47.5 per foot 47.5 213.75
4 Ordinary labour (B) Cost of accessories: Machineries charges 1 LS 550 per day 550 550
5 Ordinary labour Bolts & nuts 1 LS 550 per day 440 440
6 Skilled technician (C) Labour charge for fabrication, assembling and fitting-fixing in position : Skilled technician 0.33 no 1200 per day 1200 396
7 Semi skilled technician Semi- skilled technician 0.33 no 800 per day 800 264
8 Ordinary labour Tools and plant, sundries etc. 1 LS 550 per day 330 330
Sub-Total 8195.25
Contractor's Profit 10% 0.1 819.53
Contractor's Overhead Expenses 3.5% 0.035 286.83
Total 9301.61
Add VAT with adjustment factor. 1.08108 7.5% 0.075 754.18
Grand Total 10055.79
Rate per sft 1117.33
Rate per sqm 12026.94