Considering 1 No. partition Considering 5'-0" x 4'-0"= 20 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 5 mm reflective glass (A) Materials: 5 mm thick reflective glass | 20 | sft | 102 | sft | 102 | 2040 | |
| 2 | 5 mm reflective glass Wastage 5% | 1 | sft | 102 | sft | 102 | 102 | |
| 3 | Rubber gasket Neoprene / rubber gasket | 20 | rft | 2 | rft | 2 | 40 | |
| 4 | Ordinary labour Local carriage | 1 | LS | 550 | per day | 110 | 110 | |
| 5 | Ordinary labour (B) Labour charges: Labour cost for fitting and fixing in position of 5 mm thick tinted glass in aluminium frame, partitions and windows. | 20 | sft | 550 | per day | 11 | 220 | |
| Sub-Total | 2512 | |||||||
| Contractor's Profit | 10% | 0.1 | 251.2 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 87.92 | |||||
| Total | 2851.12 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 231.17 | ||||
| Grand Total | 3082.29 | |||||||
| Rate per sft | 154.1 | |||||||
| Rate per sqm | 1658.73 | |||||||