Considering 1 No. partition Considering 5'-0" x 4'-0"= 20 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 6 mm reflective tempered glass (A) Materials: 6 mm thick reflecting tempered glass | 20 | sft | 187 | sft | 187 | 3740 | |
| 2 | 6 mm reflective tempered glass Wastage 5% | 1 | sft | 187 | sft | 187 | 187 | |
| 3 | Rubber gasket Neoprene / Rubber gasket | 20 | rft | 2 | rft | 2 | 40 | |
| 4 | Ordinary labour Local carriage and sundries | 1 | LS | 550 | per day | 110 | 110 | |
| 5 | Ordinary labour (B) Labour charges: Labour cost for fitting and fixing in position of 6 mm thick clear glass in aluminium frame,partitions and windows. | 20 | sft | 550 | per day | 11 | 220 | |
| Sub-Total | 4297 | |||||||
| Contractor's Profit | 10% | 0.1 | 429.7 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 150.4 | |||||
| Total | 4877.1 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 395.44 | ||||
| Grand Total | 5272.54 | |||||||
| Rate per sft | 263.65 | |||||||
| Rate per sqm | 2837.93 | |||||||