Considering (1 m x 2 m)
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Sign board including material, painting,lettering etc all complete Cost of sign board including painting, lettering etc. | 21.52 | sft | 250 | sft | 250 | 5380 | |
| 2 | Skilled labour Skilled labour for hoisting | 1 | nos | 600 | per day | 600 | 600 | |
| 3 | Skilled labour Skilled labour for removing after completion of contract | 1 | nos | 600 | per day | 600 | 600 | |
| Sub-Total | 6580 | |||||||
| Contractor's Profit | 10% | 0.1 | 658 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 230.3 | |||||
| Total | 7468.3 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 605.54 | ||||
| Grand Total | 8073.84 | |||||||
| Rate per sqm | 4037 | |||||||
| Rate per sqm | 4037 | |||||||