Breakup

01.1.5 Providing and maintenance one project profile signboards to be placed at a suitable place of the site including submission of proposals for the materials of the signboards and text layout containing 3D picture, safety instructions, project information with security light etc to the Engineer-in-charge for approval which will be positioned as directed by the Engineer-in-charge and removing the same on completion of the works or as instructed by the Engineer-in-charge.

Considering (1 m x 2 m)

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Sign board including material, painting,lettering etc all complete Cost of sign board including painting, lettering etc. 21.52 sft 250 sft 250 5380
2 Skilled labour Skilled labour for hoisting 1 nos 600 per day 600 600
3 Skilled labour Skilled labour for removing after completion of contract 1 nos 600 per day 600 600
Sub-Total 6580
Contractor's Profit 10% 0.1 658
Contractor's Overhead Expenses 3.5% 0.035 230.3
Total 7468.3
Add VAT with adjustment factor. 1.08108 7.5% 0.075 605.54
Grand Total 8073.84
Rate per sqm 4037
Rate per sqm 4037