Considering 1 No. partition Considering 5'-0" x 4'-0"= 20 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 12 mm clear tempered glass (A) Materials: 12 mm thick clear tempered glass | 20 | sft | 400 | sft | 400 | 8000 | |
| 2 | 12 mm clear tempered glass Wastage 5% | 1 | sft | 400 | sft | 400 | 400 | |
| 3 | Rubber gasket Neoprene / Rubber gasket | 20 | rft | 2 | rft | 2 | 40 | |
| 4 | Ordinary labour Local carriage and sundries | 1 | LS | 550 | per day | 110 | 110 | |
| 5 | Ordinary labour (B) Labour charges: Labour cost for fitting and fixing in position of 12 mm thick clear glass in aluminium frame,partitions and windows. | 20 | sft | 550 | per day | 22 | 440 | |
| Sub-Total | 8990 | |||||||
| Contractor's Profit | 10% | 0.1 | 899 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 314.65 | |||||
| Total | 10203.65 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 827.32 | ||||
| Grand Total | 11030.97 | |||||||
| Rate per sft | 551.55 | |||||||
| Rate per sqm | 5936.88 | |||||||