Considering 1 No. partition Considering 5'-0" x 4'-0"= 20 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 8 mm low-E clear tempered glass (A) Materials: (8 mm thick clear tempered Low-E glass=20sft + Wastage 5%=1sft)=21sft | 21 | sft | 355 | sft | 355 | 7455 | |
| 2 | 8 mm clear tempered glass (8 mm thick clear tempered glass=20sft + Wastage 5% =1sft) =21sft | 21 | sft | 255 | sft | 255 | 5355 | |
| 3 | 1.52 mm thick PVB lamination PVB Lamination(1.52mm) cost | 20 | rft | 250 | per foot | 250 | 5000 | |
| 4 | Ordinary labour Local carriage and sundries | 1 | LS | 550 | per day | 165 | 165 | |
| 5 | Ordinary labour (B) Labour charges: Labour cost for fitting and fixing in position of 17.52 mm thick clear glass in aluminium frame,partitions and windows. | 20 | sft | 550 | per day | 44 | 880 | |
| Sub-Total | 18855 | |||||||
| Contractor's Profit | 10% | 0.1 | 1885.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 659.93 | |||||
| Total | 21400.43 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1735.17 | ||||
| Grand Total | 23135.6 | |||||||
| Rate per sft | 1156.8 | |||||||
| Rate per sqm | 12451.8 | |||||||