Breakup

02.18.1 For initial lead of 30 m and lift of 1.5 m

Considering 1000 cft of excavation work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour For initial lead of 100'-0" and lift of 5'-0" : Ordinary labour 11 nos 550 per day 550 6050
2 Head mason / Mosaic head mistry Sardar 0.5 no 800 per day 800 400
3 Tools & plants (spade, busket) etc. LS 48
Sub-Total 6498
Contractor's Profit 10% 0.1 649.8
Contractor's Overhead Expenses 3.5% 0.035 227.43
Total 7375.23
Add VAT with adjustment factor. 1.08108 7.5% 0.075 597.99
Grand Total 7973.22
Rate per cft 7.97
Rate per cum 281.46