Considering 1 No. partition Considering 5'-0" x 4'-0"= 20 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 6 mm clear tempered glass (A) Materials: (6 mm thick clear tempered clear glass 40sft + Wastage 5%=2sft)=42sft | 42 | sft | 190 | sft | 190 | 7980 | |
| 2 | Argon gas charge for double glazing glass Argon gas charge | 20 | sft | 30 | sft | 30 | 600 | |
| 3 | Insulated Gum/Structural silicon for Gas sealing in double glazing glass Insulated Gum/Structural silicon for Gas sealing | 20 | sft | 70 | sft | 70 | 1400 | |
| 4 | Aluminium slp,desiccant(silica gel) for double glazing glass Aluminium slp,desiccant(silica gel) etc. | 20 | sft | 50 | sft | 50 | 1000 | |
| 5 | Ordinary labour Local carriage and sundries | 1 | LS | 550 | per day | 110 | 110 | |
| 6 | Ordinary labour (B) Labour charges: Labour cost for fitting and fixing in position of 24 mm thick clear glass in aluminium frame, partitions and windows | 20 | sft | 550 | per day | 49.5 | 990 | |
| Sub-Total | 12080 | |||||||
| Contractor's Profit | 10% | 0.1 | 1208 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 422.8 | |||||
| Total | 13710.8 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1111.69 | ||||
| Grand Total | 14822.49 | |||||||
| Rate per sft | 741.1 | |||||||
| Rate per sqm | 7977.2 | |||||||