Considering 1000 cft of excavation work For initial lead of 100'-0" and lift of 5'-0"
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Ordinary labour Extra labour | 0.5 | no | 550 | per day | 550 | 275 | |
| Sub-Total | 275 | |||||||
| Contractor's Profit | 10% | 0.1 | 27.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 9.63 | |||||
| Total | 312.13 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 25.31 | ||||
| Grand Total | 337.44 | |||||||
| Rate per cft | 0.34 | |||||||
| Rate per cum | 12.01 | |||||||