02.18.2 Added for each additional lift of 0.3 m beyond 1.5 m and up to 3 m

Considering 1000 cft of excavation work For initial lead of 100'-0" and lift of 5'-0"

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Extra labour 0.5 no 550 per day 550 275
Sub-Total 275
Contractor's Profit 10% 0.1 27.5
Contractor's Overhead Expenses 3.5% 0.035 9.63
Total 312.13
Add VAT with adjustment factor. 1.08108 7.5% 0.075 25.31
Grand Total 337.44
Rate per cft 0.34
Rate per cum 12.01