Breakup

15.2 Minimum 12 mm thick cement sand (F.M. 1.2) plaster with neat cement finishing to plinth wall with cement (1:4) up to 150 mm below ground level including washing of sand, finishing the edges and corners and curing at least for 7 days, cost of water, electricity, scaffolding and other charges etc. all complete in all respect as per drawing and accepted by the Engineer-in-charge. (Cement: CEM-II/B-M) ground floor.

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Sand (F.M. 1.2) Sand (F.M. 1.2) 5 cft 1900 per % cft 19 95
2 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement 1.5 bag 410 per bag 410 615
3 Head mason / Mosaic head mistry Labour : Head mason 0.25 no 800 per day 800 200
4 Mason / Mosaic mistry Mason 1.25 no 700 per day 700 875
5 Ordinary labour Ordinary labour 1.25 no 550 per day 550 687.5
6 Ordinary labour Washing of sand, local carriage, curing, & sundries etc. 1 LS 550 per day 366.67 366.67
Sub-Total 2839.17
Contractor's Profit 10% 0.1 283.92
Contractor's Overhead Expenses 3.5% 0.035 99.37
Total 3222.46
Add VAT with adjustment factor. 1.08108 7.5% 0.075 261.28
Grand Total 3483.74
Rate per sft 34.84
Rate per sqm 375.02