Considering 1000 cft of excavation work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Ordinary labour Extra labour | 0.75 | no | 550 | per day | 550 | 412.5 | |
| Sub-Total | 412.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 41.25 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 14.44 | |||||
| Total | 468.19 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 37.96 | ||||
| Grand Total | 506.15 | |||||||
| Rate per cft | 0.51 | |||||||
| Rate per per cum | 18.01 | |||||||