15.5 Minimum 6 mm thick cement sand (F.M. 1.2) plaster (1:4) with fresh cement to ceiling, R.C.C. columns, beams, surface of stair case, sunshades, cornices, railings, drop wall, louvers, fins and finishing the corners and edges including washing of sand, cleaning the surface, curing at least for 7 days, cost of water, electricity, scaffolding and other charges etc. all complete in all respect as per drawing and accepted by the Engineer-in-charge. (Cement: CEM-II/B-M) ground floor.

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Sand (F.M. 1.2) Sand (F.M. 1.2) 2.5 cft 1900 per % cft 19 47.5
2 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement 0.5 bags 410 per bag 410 205
3 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Extra cement for grouting 0.125 bag 410 per bag 410 51.25
4 Head mason / Mosaic head mistry Labour : Head mason 0.25 no 800 per day 800 200
5 Mason / Mosaic mistry Mason 1 no 700 per day 700 700
6 Ordinary labour Ordinary labour 1 no 550 per day 550 550
7 Ordinary labour Extra labour for chiping RCC surface 0.5 no 550 per day 550 275
8 Ordinary labour Washing of sand, scaffolding, curing, sundries, local carriage etc. 1 LS 550 per day 366.67 366.67
Sub-Total 2395.42
Contractor's Profit 10% 0.1 239.54
Contractor's Overhead Expenses 3.5% 0.035 83.84
Total 2718.8
Add VAT with adjustment factor. 1.08108 7.5% 0.075 220.44
Grand Total 2939.24
Rate per sft 29.39
Rate per sqm 316.35