Considering 25 rft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Sand (F.M. 1.2) Sand (F.M. 1.2) | 0.52 | cft | 1900 | per % cft | 19 | 9.88 | |
| 2 | Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement | 0.08 | bag | 410 | per bag | 410 | 32.8 | |
| 3 | Mason / Mosaic mistry Labour : Mason | 1 | no | 700 | per day | 700 | 700 | |
| 4 | Ordinary labour Ordinary labour | 0.5 | no | 550 | per day | 550 | 275 | |
| 5 | Ordinary labour Washing of sand, scaffolding, curing, sundries, local carriage etc. | 1 | LS | 550 | per day | 36.67 | 36.67 | |
| Sub-Total | 1054.35 | |||||||
| Contractor's Profit | 10% | 0.1 | 105.44 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 36.9 | |||||
| Total | 1196.69 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 97.03 | ||||
| Grand Total | 1293.72 | |||||||
| Rate per rft | 51.76 | |||||||
| Rate per rm | 169.82 | |||||||