Breakup

15.11.1 Making groove in plaster on outside wall upto 50 mm X 6 mm size including scaffolding, curing etc. complete as per drawing and accepted by the Engineer-in-charge.

Consideration 20'-0" work Size of groove 2" X 1/4"

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Mason / Mosaic mistry Labour Cost: a) Mason 0.125 no 700 per day 700 87.5
2 Ordinary labour b) Ordinary Labour 0.125 no 550 per day 550 68.75
3 Ordinary labour Scaffolding, Tools, Sundries etc. 1 LS 550 per day 10 10
Sub-Total 166.25
Contractor's Profit 10% 0.1 16.63
Contractor's Overhead Expenses 3.5% 0.035 5.82
Total 188.7
Add VAT with adjustment factor. 1.08108 7.5% 0.075 15.3
Grand Total 204
Rate per rft 10.2
Rate per rm 33.47