Breakup

15.11.2 Making groove in plaster on outside wall upto 38 mm X 6 mm size including scaffolding, curing etc. complete as per drawing and accepted by the Engineer-in-charge.

Break-up for 25 rft

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Mason / Mosaic mistry Mason 0.1875 no 700 per day 700 131.25
2 Skilled labour Skilled labour 0.1875 no 600 per day 600 112.5
3 Ordinary labour Curing, tools and plant, sundries 1 LS 550 per day 55 55
Sub-Total 298.75
Contractor's Profit 10% 0.1 29.88
Contractor's Overhead Expenses 3.5% 0.035 10.46
Total 339.09
Add VAT with adjustment factor. 1.08108 7.5% 0.075 27.49
Grand Total 366.58
Rate per rft 14.68
Rate per rm 48.17