Break-up for 25 rft
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Mason / Mosaic mistry Mason | 0.1875 | no | 700 | per day | 700 | 131.25 | |
| 2 | Skilled labour Skilled labour | 0.1875 | no | 600 | per day | 600 | 112.5 | |
| 3 | Ordinary labour Curing, tools and plant, sundries | 1 | LS | 550 | per day | 55 | 55 | |
| Sub-Total | 298.75 | |||||||
| Contractor's Profit | 10% | 0.1 | 29.88 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 10.46 | |||||
| Total | 339.09 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 27.49 | ||||
| Grand Total | 366.58 | |||||||
| Rate per rft | 14.68 | |||||||
| Rate per rm | 48.17 | |||||||