Breakup

02.18.4 Added for each additional lift of 0.3 m beyond 4.5 m and up to 6 m

Considering 1000 cft of excavation work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Extra labour 1 no 550 per day 550 550
Sub-Total 550
Contractor's Profit 10% 0.1 55
Contractor's Overhead Expenses 3.5% 0.035 19.25
Total 624.25
Add VAT with adjustment factor. 1.08108 7.5% 0.075 50.61
Grand Total 674.86
Rate per cft 0.68
Rate per per cum 24.01