Consideration 20'-0" work Size of groove 2" X 1/4"
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Mason / Mosaic mistry Labour Cost: Mason | 0.125 | no | 700 | per day | 700 | 87.5 | |
| 2 | Ordinary labour Ordinary Labour | 0.125 | no | 550 | per day | 550 | 68.75 | |
| 3 | Cementetious pinhole filler Cementitious pinhole filler | 1 | kg | 100 | per kg | 100 | 100 | |
| 4 | Scaffolding, Tools, Sundries etc. | LS | 20 | |||||
| Sub-Total | 276.25 | |||||||
| Contractor's Profit | 10% | 0.1 | 27.63 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 9.67 | |||||
| Total | 313.55 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 25.42 | ||||
| Grand Total | 338.97 | |||||||
| Rate per rft | 16.95 | |||||||
| Rate per rm | 55.61 | |||||||