Breakup

15.15.1 Minimum 12mm thick cement sand (F.M-1.2) water proof, damp proof, dry and breathable plaster (1:4) with water proof Izonil Cement (STN-EN -1015-11 , Compressive Strength 34 MPa ,Max depth of water penetration into hardened plaster is < 1 mm) or equivalent compound to wall surface, finishing the corner and edges including washing of sand, cleaning the surface, scaffolding and curing at least for 3 days, cost of water, electricity and other charges etc. all complete in all respect as per drawing and accepted by the Engineer –in-charge. (Izonil Cement/equivalent compound: Water proof, damp proof, dry and breathable cement).

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Water proof, damp proof, dry & breathable cement STN-EN - 1015-11 , compressive strength 34 MPa), Max depth of water penetration into hardened plaster is < 1 mm (25 kg bag)(Only for plaster work) water proof, dampproof, dry & breathable cement 1.52 bags 1800 per bag 1800 2736
2 Sand (F.M. 1.2) Sand (F.M. 1.2) 5.25 cft 1900 per % cft 19 99.75
3 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement 0.28 bags 410 per bag 410 114.8
4 Head mason / Mosaic head mistry Labour : Head mason 0.25 no 800 per day 800 200
5 Mason / Mosaic mistry Mason 1 no 700 per day 700 700
6 Ordinary labour Ordinary labour 1 no 550 per day 550 550
7 Hire charge of concrete mixer machine Hire charge of concrete mixer machine 0.1 no 1200 per day 1200 120
8 Ordinary labour Washing of sand, local carriage, scaffolding, curing, & sundries etc. 1 LS 550 per day 366.67 366.67
Sub-Total 4887.22
Contractor's Profit 10% 0.1 488.72
Contractor's Overhead Expenses 3.5% 0.035 171.05
Total 5546.99
Add VAT with adjustment factor. 1.08108 7.5% 0.075 449.76
Grand Total 5996.75
Rate per sft 59.97
Rate per sqm 645.52
Help