Breakup

15.16 Added rate for plaster and all types of pointing for additional floor above ground floor

Considering 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Add for each addl. floor above ground floor ( @ 1/5 no lab. per % sft) 1 per sqm 550 per day 14.53 14.53
Sub-Total 14.53
Contractor's Profit 10% 0.1 1.45
Contractor's Overhead Expenses 3.5% 0.035 0.51
Total 16.49
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1.34
Grand Total 17.83
Rate per sft 0.18
Rate per sqm 1.94