Break-up for 100 sft Area
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Painter Painter | 2 | no | 700 | per day | 700 | 1400 | |
| 2 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper | 2 | no | 550 | per day | 550 | 1100 | |
| 3 | Ordinary labour Cleaning surface with sand paper, scaffolding, tools and plant etc. : | 1 | LS | 550 | per day | 171.88 | 171.88 | |
| 4 | Ordinary labour Application tool | 1 | LS | 550 | per day | 601.56 | 601.56 | |
| 5 | Ready-mix putty ( interior) Ready-mix putty | 3.5 | kg | 80 | per kg | 80 | 280 | |
| 6 | Sealer for acrylic plastic emulsion paint Sealer | 1.5 | liter | 172 | per litre | 172 | 258 | |
| 7 | Design Paint including base coat , design coat & protection coat Interior design paint (including base coat, design coat and protection coat) | 5 | liter | 417 | per litre | 417 | 2085 | |
| Sub-Total | 5896.44 | |||||||
| Contractor's Profit | 10% | 0.1 | 589.64 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 206.38 | |||||
| Total | 6692.46 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 542.63 | ||||
| Grand Total | 7235.09 | |||||||
| Rate per sft | 72.35 | |||||||
| Rate per sqm | 778.78 | |||||||