Considering 100 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Painter Painter | 1 | no | 700 | per day | 700 | 700 | |
| 2 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper | 1 | no | 550 | per day | 550 | 550 | |
| 3 | Chlorinated rubber paint Chlorinated rubber paint | 1.1 | liter | 638 | per litre | 638 | 701.8 | |
| 4 | Chlorinated rubber sealer Sealer / under-coat | 1.1 | liter | 503 | per litre | 503 | 553.3 | |
| 5 | Chlorinated rubber paint thinner Thinner | 0.6 | liter | 208 | per litre | 208 | 124.8 | |
| 6 | Ordinary labour Scaffolding, sundries etc. | 1 | LS | 550 | per day | 247.5 | 247.5 | |
| Sub-Total | 2877.4 | |||||||
| Contractor's Profit | 10% | 0.1 | 287.74 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 100.71 | |||||
| Total | 3265.85 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 264.8 | ||||
| Grand Total | 3530.65 | |||||||
| Rate per sft | 35.31 | |||||||
| Rate per sqm | 380.08 | |||||||