Considering 100 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Painter Painter | 1 | no | 700 | per day | 700 | 700 | |
| 2 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper | 1 | no | 550 | per day | 550 | 550 | |
| 3 | Ordinary labour Scaffolding, sundries etc. | 1 | LS | 550 | per day | 247.5 | 247.5 | |
| 4 | Epoxy enamel primer including base, curing agent & thinner Epoxy enamel primer (Base+curing agent+thinner) | 1.5 | liter | 520 | per litre | 520 | 780 | |
| 5 | Epoxy enamel paint including base, curing agent & thinner Epoxy enamel paint (Base+curing agent+thinner) | 2 | liter | 450 | per litre | 450 | 900 | |
| Sub-Total | 3177.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 317.75 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 111.21 | |||||
| Total | 3606.46 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 292.42 | ||||
| Grand Total | 3898.88 | |||||||
| Rate per sft | 38.99 | |||||||
| Rate per sqm | 419.69 | |||||||