Considering 1 day operation = 8 hrs.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Hire charge of 1 cusec capacity diesel operated water pump Hire charge of pump including suction and delivery pipe, connection, switch | 1 | day | 1300 | per day | 1300 | 1300 | |
| 3 | Machine operator Pump operator | 1 | no | 700 | per day | 700 | 700 | |
| 4 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper | 1 | no | 550 | per day | 550 | 550 | |
| 5 | Skilled labour Skilled labour for maintaining drainage | 1 | no | 600 | per day | 600 | 600 | |
| 6 | Ordinary labour Provide drainage facilities and connection to discharge system | 1 | LS | 550 | per day | 429.69 | 429.69 | |
| 7 | Ordinary labour Tools and plant, sundries etc. | 1 | LS | 550 | per day | 257.81 | 257.81 | |
| 2 | Fuel, lubricant, spares, maintenance etc. | LS | 600 | |||||
| Sub-Total | 4437.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 443.75 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 155.31 | |||||
| Total | 5036.56 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 408.37 | ||||
| Grand Total | 5444.93 | |||||||
| Rate per hour | 680.63 | |||||||
| Rate per hour | 680.63 | |||||||