Considering 100 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Painter Painter | 1 | no | 700 | per day | 700 | 700 | |
| 2 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper | 1 | no | 550 | per day | 550 | 550 | |
| 3 | Ordinary labour Scaffolding, sundries etc. | 1 | LS | 550 | per day | 495 | 495 | |
| 4 | Epoxy enamel primer including base, curing agent & thinner Epoxy enamel primer (Base+curing agent+thinner) | 1.5 | liter | 520 | per litre | 520 | 780 | |
| 5 | Epoxy enamel paint including base, curing agent & thinner Epoxy enamel paint (Base+curing agent+ thinner) | 2 | liter | 450 | per litre | 450 | 900 | |
| Sub-Total | 3425 | |||||||
| Contractor's Profit | 10% | 0.1 | 342.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 119.88 | |||||
| Total | 3887.38 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 315.19 | ||||
| Grand Total | 4202.57 | |||||||
| Rate per sft | 42.03 | |||||||
| Rate per sqm | 452.41 | |||||||