Considering 100 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Painter Painter | 1 | no | 700 | per day | 700 | 700 | |
| 2 | Helper to carpenter/painter/plumber/rod binder/electrician/polish mistry/rig operator Helper | 1 | no | 550 | per day | 550 | 550 | |
| 3 | Ordinary labour Cleaning surface with Scaffolding, local carriage, sundries etc. | 1 | LS | 550 | per day | 247.5 | 247.5 | |
| 4 | Premium Silicon based paint/coating Silicon based paint | 2 | liter | 950 | per litre | 950 | 1900 | |
| Sub-Total | 3397.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 339.75 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 118.91 | |||||
| Total | 3856.16 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 312.66 | ||||
| Grand Total | 4168.82 | |||||||
| Rate per sft | 41.69 | |||||||
| Rate per sqm | 448.75 | |||||||